Periodic Inspection of Energy Control Procedure
29 CFR 1910.147(c)(6) · Complete at least once a year for each procedure
Equipment and procedure
Inspector
Must be an authorized employee other than the people using this procedure. (c)(6)(i)(A)
Employees included in the inspection
| Name | Role | Responsibilities reviewed | Remove |
|---|---|---|---|
Inspection checklist
Observe the procedure being used, or walk through it with the authorized employees.
| Item | Result | Notes |
|---|---|---|
| 1. Procedure is written for this machine and is the current version (c)(4)(i) | ||
| 2. Every energy source and its magnitude is listed (c)(4)(ii) | ||
| 3. Shutdown steps were followed in the order written (d)(2) | ||
| 4. Every energy-isolating device was located and operated as written (d)(3) | ||
| 5. Each authorized employee applied their own lock or tag at every isolation point (d)(4) | ||
| 6. Stored or residual energy was relieved, disconnected, or restrained (d)(5) | ||
| 7. Isolation was verified before work began (d)(6) | ||
| 8. Locks and tags are standardized, durable, and identify who applied them (c)(5) | ||
| 9. Release steps were followed: area cleared, employees notified, devices removed by the person who applied them (e) | ||
| 10. Each authorized employee could explain their responsibilities under this procedure (c)(6)(i)(C) |
Findings and corrective action
Certification
I certify that I performed the periodic inspection of the energy control procedure listed above, as required by 29 CFR 1910.147(c)(6)(ii), on the date shown, with the employees listed.