Contractor and Shift-Change LOTO: Keeping Protection Continuous

To keep lockout/tagout protection continuous, the host employer and outside contractors must inform each other of their energy control procedures (1910.147(f)(2)), and shift or personnel changes need a specific procedure for the orderly transfer of lockout or tagout protection (1910.147(f)(4)).

This guide summarizes those requirements and describes group lockout as one possible method. The employer must choose a method that fits the actual work.

The outside-personnel rule: brief both ways

Under 1910.147(f)(2), when outside servicing personnel perform covered activities, the on-site employer and outside employer must inform each other of their respective lockout/tagout procedures. Each employer must ensure its employees understand and comply with the applicable restrictions and prohibitions.

Coordinate the actual procedure, equipment boundaries, responsibilities, and protection method before covered work begins. A group lockbox is one possible group method; the standard does not prescribe one universal arrangement.

Host vs contractor: who owes what

The standard requires both employers to exchange their procedures and ensure their own employees understand and follow the other employer’s applicable restrictions. Agree who supplies the machine-specific information, who performs each part of the employer-approved procedure, and how each exposed employee receives required protection.

Use the actual employer relationship, work scope, and applicable OSHA requirements to assign responsibilities. A contract or briefing does not replace required energy controls, training, or coordination.

Temp and staffing-agency workers

Determine each temporary worker’s role from the work performed and exposure: authorized, affected, or other. The employer responsible for the worker’s training must ensure the training required by 1910.147(c)(7); employers must coordinate site-specific information and outside-servicing procedures where 1910.147(f)(2) applies.

Do not assume that a general orientation alone covers equipment-specific procedures or that one employer’s briefing automatically fulfills another employer’s obligations. Document the training and coordination process used at the site.

Shift and personnel changes: maintain protection during transfer

Section 1910.147(f)(4) requires procedures for orderly transfer of lockout/tagout protection during shift or personnel changes. The employer must select a method that maintains continuity of protection; overlapping personal locks during a handover is one possible method when it fits the employer’s group procedure.

Make sure employees understand when responsibility transfers and how each employee’s protection is maintained. Follow the employer’s written procedure and applicable group-lockout requirements; this article does not prescribe a universal handover sequence or record form.

Records and coordination to review

When reviewing the program, check that the applicable outside-servicing procedures were exchanged, employees were informed of the relevant restrictions, group protection met the employer’s procedure, and protection was transferred as required. The standard does not prescribe a particular briefing form or shift log.

Use the compliance checklist as an internal planning aid. Confirm that any records you keep reflect the actual procedure and employer requirements.

Frequently asked questions

Do contractors follow our LOTO procedure or theirs?

Under 1910.147(f)(2), both employers inform each other of their respective procedures and ensure their employees understand and comply with the other employer’s applicable restrictions. Coordinate the actual equipment, work, and protection method before servicing begins.

How do shift changes work during a lockout?

The employer must have procedures for orderly transfer of protection under 1910.147(f)(4). Overlapping locks can be one method, but follow the site’s documented process and ensure protection remains continuous during the transfer.

Who trains temp workers on lockout/tagout?

Determine the worker’s role from the work and exposure, then ensure the employer responsible provides the training required by 1910.147(c)(7). Coordinate site-specific procedures and restrictions between employers when 1910.147(f)(2) applies.

Can the host isolation cover the contractor crew?

The employer’s group lockout method must provide the protection required by 1910.147(f)(3). One possible method is for each authorized employee to place a personal lock on a group lockbox or equivalent mechanism; the primary authorized employee and each group member have responsibilities defined by the standard. The exact method depends on the work and employer procedure.