The 6 Lockout/Tagout Steps and Zero-Energy Check

The six lockout/tagout steps in OSHA 1910.147(d) are: prepare for shutdown, shut down the equipment, isolate energy sources, apply lockout or tagout devices, control stored energy, and verify isolation (the zero-energy check) before work begins.

Affected-employee notification is covered in 1910.147(c)(9) and return to service in 1910.147(e). This guide summarizes the requirements; the employer’s procedure supplies the equipment-specific steps.

The six steps in order

Section 1910.147(d) lists these application actions. Use the employer’s machine-specific procedure for the actual equipment and task:

  • 1. Prepare for shutdown: the authorized employee knows the energy type and magnitude, its hazards, and the means to control it.
  • 2. Shut down: use the equipment-specific shutdown procedure and avoid additional hazards.
  • 3. Isolate: locate and operate all energy-isolating devices needed to isolate the equipment.
  • 4. Apply devices: authorized employees apply lockout or tagout devices as specified in the employer’s procedure.
  • 5. Control stored or residual energy: relieve, disconnect, restrain, or otherwise render it safe under the procedure; account for reaccumulation.
  • 6. Verify: before work begins, an authorized employee verifies isolation and deenergization using the procedure’s method.

Steps 1–2: notify, then shut down normally

Under 1910.147(c)(9), affected employees are notified before lockout or tagout devices are applied and after they are removed. Follow the employer’s communication procedure.

Section 1910.147(d)(2) requires shutdown using the machine-specific procedure and an orderly shutdown that avoids additional hazards. Use the employer’s instructions for the equipment.

Steps 3–4: isolate everything, then lock it

The authorized employee locates and operates all energy-isolating devices needed to isolate the equipment. Use the employer’s assessment and procedure to identify sources; do not rely on a generic list.

Apply devices according to the employer’s lockout or tagout program. Group work must follow the group method required by 1910.147(f)(3); a group lockbox is one common method.

Step 5: release what isolation leaves behind

Follow the employer’s procedure to relieve, disconnect, restrain, or otherwise render potentially hazardous stored or residual energy safe. The appropriate control depends on the equipment and work.

Do not copy a release method, device identifier, or measurement value from a generic example. The employer’s procedure must specify controls verified for the actual equipment.

Step 6: verify isolation and deenergization

Under 1910.147(d)(6), an authorized employee verifies isolation and deenergization before starting work. Follow the method in the employer’s procedure and applicable safety rules. There is no universal three-check sequence for every machine.

QuestionWhat to follow
Is the required energy control effective?Use the equipment-specific verification method in the employer’s procedure.
Could stored energy remain or reaccumulate?Follow the procedure and 1910.147(d)(5) for release, restraint, and continued verification.
Could employees be exposed to electrical parts?Follow the applicable electrical safety rules and qualified-person testing procedure; a try-start alone is not an electrical test.

Return to service without creating the next incident

Before devices are removed, follow 1910.147(e): check the work area and equipment, ensure employees are safely positioned or removed, remove devices under the standard and employer procedure, and notify affected employees before restart.

The employee who applied a device ordinarily removes it. If that employee is unavailable, the employer may direct removal only under the specific documented and trained procedure in 1910.147(e)(3).

Frequently asked questions

What are the six steps of lockout/tagout?

The application actions are preparation, shutdown, isolation, device application, stored-energy control, and verification under 1910.147(d). Notify affected employees as required by (c)(9). Follow (e) and the employer’s procedure for return to service.

What is the try-start check?

A try-start means operating the normal controls when the employer’s procedure calls for that check. It can show whether the equipment responds to those controls, but it does not establish that electrical conductors are deenergized or verify all other energy sources. Follow the site procedure.

How do you verify zero energy on multi-energy machines?

Follow the employer’s equipment-specific procedure and applicable safety rules. The method must address all relevant energy sources and stored or residual energy. Do not infer a verification method from a general energy category.

Can the disconnect be used to stop the machine?

The standard requires shutdown using the machine-specific procedure and an orderly shutdown that avoids additional hazards. Follow the employer’s instructions for the equipment; do not use a generic article to decide how to stop it.